Update
Waste Options
Photo courtesy of Anchorage Solid Waste Services
Photo courtesy of Anchorage Solid Waste Services
Waste Options
nchorage is running out of space for its trash. The city’s existing central transfer station, or CTS, started life as a garbage shredder and was never meant to serve as a waste transfer station. Meanwhile, the municipality’s 275-acre regional landfill is steadily filling—and once it does, there’s no place for a new landfill site.
That’s why Anchorage Solid Waste Services, or SWS, is working on several projects that will extend the life of the regional landfill by twenty years or more and provide recycling and waste diversion options that will save Anchorage residents money in the long-term.
“It behooves us to take care of the landfill we have because once it’s gone, solid waste costs will increase,” says Mark Spafford, SWS general manager.
To that end, SWS has several projects in the works. Cruz Construction completed SWS’s newest landfill cell last year, and Davis Constructors is managing the development of a new CTS. At the same time, Cornerstone General Contractors is rebuilding an SWS facility damaged in the 2018 earthquake.
“Because of how much garbage is accumulated, every four or five years we have to do a landfill cell expansion,” explains Michael Rhodes, SWS manager of engineering and planning. SWS is currently permitted a total of twelve cells.
Last year, Cruz Construction completed cell 9a—a new, lined landfill cell—by excavating material from a 14.5 acre site and lining the bottom and sides of the cell with high-density polyethelene plastic. Cruz also built a leachate collection system for the cell.
The material removed from cell 9a will be used to cover garbage in existing cells, since trash dumped at the landfill must be covered with six inches of dirt to prevent the elements or animals from disrupting the refuse.
The remaining two cells at the landfill will be excavated, lined, and ready for use by 2025, says Rhodes.
Cornerstone is replacing the previous concrete masonry unit, or CMU, block administration building with a pre-engineered metal building that will be safer in future seismic events.
“This is my first project with SWS,” says Cornerstone Project Manager Anthony Chen, “and they’ve been awesome to work with. This has been a very fulfilling project.”
In addition to working with FEMA to procure funding for the project, Rhodes says the biggest challenge of rebuilding the earthquake-damaged facilities has been diminished material supplies due to COVID-19.
“We had to extend that project by at least a couple months because of the bottleneck of materials,” Rhodes says, adding that the project should be complete by spring or summer 2022.
Photo courtesy of Anchorage Solid Waste Services
“We put 325 Alaskan families to work during the pandemic,” Spafford says, pointing out that the CTS will continue to provide long-term community benefits. Though solid waste service fees will rise over the next five years, even with this increase Anchorage will still have some of the lowest trash disposal fees in the state and the region.
The new $120 million CTS should be finished in late 2022 or early 2023 and is a design-build project developed by California-based Tetra Tech, Inc. Davis Constructors and Engineers is the project’s construction manager self-performing concrete, foundation, drywall, and exterior. Davis is also providing design assistance and construction for five other buildings on the 27-acre site.
In August, Davis poured 28,000 cubic yards of concrete, including a wear-resistant and chemical-resistant tipping facility floor. The tipping floor includes a suspended slab and a 16-by-28-foot wide tunnel that will allow two tractor-trailers to pull in, side by side, for filling.
The CTS structure itself is another pre-engineered building. The floors will be equipped with an ice prevention system; high-speed fabric doors will help maintain heat preservation inside the building. The building will experience up to ten air changes per hour, which should prevent the smell of trash from affecting the facility’s neighbors.
Rather than tear down the former transfer facility, SWS is converting it to a recycling center. The proximity of the two facilities will mean municipal residents can drop off their recyclables and refuse in one location. The additional space means SWS can divert even more recyclable material and organics than it currently does. “We’ll be able to add twenty years of life to the landfill just from that,” Spafford says.
Incorporating community input has been a key aspect to designing and building the new CTS. For example, city-wide eagerness to recycle glass led Spafford’s team to incorporate 6,000 yards of recycled glass aggregate into project elements like pipe bedding and road beds.
“There’s been a lot of hesitancy in the local construction industry to use recycled glass that way,” Spafford says. “With this project, we wanted to demonstrate we can use glass aggregate properly, since the biggest thing we get asked to do at SWS is to recycle glass.”
Photo courtesy of Anchorage Solid Waste Services
Incorporating community input has been a key aspect to designing and building the new CTS. For example, city-wide eagerness to recycle glass led Spafford’s team to incorporate 6,000 yards of recycled glass aggregate into project elements like pipe bedding and road beds.
“There’s been a lot of hesitancy in the local construction industry to use recycled glass that way,” Spafford says. “With this project, we wanted to demonstrate we can use glass aggregate properly, since the biggest thing we get asked to do at SWS is to recycle glass.”
Photo courtesy of Anchorage Solid Waste Services
Photo courtesy of Anchorage Solid Waste Services
Editor’s Note: This story was written in early August, when Spafford was still SWS manager. He has since resigned and Dan Zipay was appointed to the post.