hile you would expect a university dorm to be pretty quiet after students move out, there’s actually a lot of activity happening on the University of Alaska Fairbanks, or UAF, Troth Yeddha’ campus as GHEMM Company, LLC, works to complete two large construction projects designed to enhance the student experience.
Photo provided by UAF
In 2021, Bettisworth North Architects and Planners, Inc. worked in collaboration with the UAF User Design Committee to envision the space. GHEMM Company, LLC, won the bid through a low lump sum bid contracting method and began construction in June of 2023.
Photo provided by Ken Graham
Work is expected to be completed in early August, with close-outs and cleaning to follow.
Wohlford says the $32.5 million project has been on the books for ten years and includes removing and replacing the plumbing infrastructure, redoing the restrooms, and relocating laundry rooms. GHEMM will also do a finish facelift inside each dorm room that includes painting and new floors, as well as new flooring in the corridors.
“As soon as the students moved out, we moved in,” says Nordale. “It’s a tight timeline. Each building is eight floors for a total of sixteen floors, and we’re touching every floor.”
Not surprisingly, there were a number of code upgrades that were not anticipated in the work on the 60-year-old buildings, increasing the cost of the job.
“Unfortunately, the timeline hasn’t changed—we still have to be done when school starts in fall 2024,” says Nordale. “For us, that’s the biggest challenge.”
The GHEMM crew are systematically working their way from the top to the bottom of each building, with builders framing walls on one floor while electricians and plumbers work on another. Sheetrock, ceramic tile, and painting work follow behind.
“It’s like a train moving through each building, and when we come across unexpected conditions we have to fix, it causes hiccups,” says Nordale. “But, at the end of the day, we have to be done because every single dorm room on the campus is full. In fact, UAF brought old dorms back online to accommodate the fact that these two are offline.”
These projects are not the first that GHEMM has completed for UAF. The company worked on the original on-site power plant, built the virology lab on the west ridge of the campus, and built an addition onto the Wood Center. It also renovated the Fine Arts Complex lobby, replaced windows in the library, and built greenhouses and a lab at the Arctic Health Center.
President, GHEMM Company
UAF Student Success Center:
- A&A Roofing Company, Inc.
- Commercial Contractors, Inc.
- Star Electric, Inc.
Moore and Bartlett complex:
- West Coast Concrete Restoration
- A&A Roofing Company, Inc.
- Commercial Contractors, Inc.
- Gundersen Painting, Inc.
- Patrick Mechanical, LLC
- Fullford Electric, Inc.