Headshot of Jedidiah K. Blake II
Jedidiah K. Blake II
Attorney, Oles Morrison
Rinker& Baker
Headshot of Sydney M. Sullivan
Sydney M. Sullivan
Attorney, Oles Morrison
Rinker& Baker
The Associated General Contractors of Alaska logo
Contractors & the law
Headshot of Jedidiah K. Blake II
Jedidiah K. Blake II
Attorney, Oles Morrison
Rinker& Baker
Headshot of Sydney M. Sullivan
Sydney M. Sullivan
Attorney, Oles Morrison
Rinker& Baker
The Associated General Contractors of Alaska logo
Contractors & the law
Legal Remedies for Contractors
Limited causes of action at the state level for contractor relief in unpredictable times
By Jedidiah K. Blake II and Sydney M. Sullivan
S

ince the onset of the COVID-19 pandemic, the construction industry has been in flux. Mandatory health and safety protocols, supply chain delays slowing down delivery of materials, and other problems combined to impact and delay projects nationwide. While the United States recovers from the pandemic, rising inflation has led to materials and fuel prices skyrocketing, which have further affected the construction industry.

With rising materials and fuel costs and continued uncertainty surrounding the pandemic and the economy, it is important that contractors are aware of legal concepts that may help recover costs incurred due to overruns, changed work, and/or delays. In addition to recovery under a force majeure clause/theory, quantum meruit and cumulative impact claims are two other potential sources of recovery. While both causes of action are applicable only in exceptional circumstances, they should be considered by contractors during and after construction when trying to recover losses suffered on a project.

Best Practices
  • Beware broad change order and lien release language that waives claims and continuing costs—especially “impact costs” and “inefficiency costs”—or may even disallow recovery under quantum meruit;
  • Raise and preserve your right for quantum meruit and/or cumulative impact costs (by reserving your rights in change orders and lien releases) as soon as practicable;
  • Make sure to follow all contract procedural provisions to ensure compliance with notice requirements and to avoid unintentional waiver of cumulative impact costs or potential quantum meruit recovery; and
  • Implement a routine practice of fighting for a provision in change orders and releases stating: “this does not waive rights to continuing impact costs and/or inefficiencies.”
Quantum Meruit
Quantum meruit is an equitable principle that means “as much as deserved,” and it arises when substantial changes occur that were not covered by the contract or contemplated by the parties. Quantum meruit provides extra contractual recovery in limited circumstances for contractors to recover the reasonable value of work on projects which suffer extraordinary delay or disruption.

In construction cases in Alaska, quantum meruit recovery requires a contractor to meet the following elements:

  1. The originally contracted work was materially changed, disrupted, and/or delayed by events for which the owner is responsible;
  2. The changes, disruptions, and/or delays were not within the reasonable contemplation of the parties;
  3. The effect of the changes, disruptions, and/or delays was to require extra work and materials or to cause substantial loss to the contractor.

All three elements must be met in order to recover. The second element can be a significant hurdle to overcome, as courts will look to the express provisions of the contract to determine whether the work in question is covered by the contract scope of work or could have been dealt with under the change order provisions. Even so, when substantial changes occur that the parties did not anticipate, contractors should consider a potential claim under quantum meruit.

Cumulative Impact Costs
Cumulative impact claims arise when multiple changes are made during a project, the magnitude of which are not realized at the time of implementation but rather in retrospect by increased costs, timing delays, difficulties in the sequencing of work, etc.

In Alaska, equitable adjustments to the contract price can—and usually do—precede a cumulative impact claim. However, a cumulative impact claim can still arise after an equitable adjustment (or even multiple adjustments or change orders) if the extent of the project delay, disruption, or damages was unknown at the time of the adjustment. A major complication for contractors is that in most cases recognition of cumulative impact is often not appreciated until after change orders, which may provide for full and final compensation, are already negotiated and executed. The problem posed is that cumulative impact claims become much more difficult to recover upon if waived in previous equitable adjustments/change orders—especially if those adjustments and change orders extended far into the project.

When pursuing a cumulative impact claim, a contractor must persuade the court that a previous change order or equitable adjustment did not waive all future claims, including claims for impact costs. This hurdle is easier to overcome for change orders and releases completed in the early stages of a project, versus releases and change orders enacted closer to substantial completion. Even so, when a multitude of changes or difficulties have occurred during a project—no matter at what stage—contractors should always consider a potential cumulative impact claim for costs.

Conclusion
With the continued impacts of the pandemic and rising materials and fuel costs affecting the construction industry, it is important for contractors to remember to utilize every cause of action available, including quantum meruit and cumulative impact claims. Other present-day examples where quantum meruit and cumulative impact claims may be applicable are with rising prices and increased delays such as concrete strikes recently experienced in Washington, rising costs and delays due to global supply chain issues, and other costs associated with current inflation. Contractors should be diligent in preserving their rights to bring impact costs and quantum meruit damages in change order and release language as a best practice. Thus, although limited causes of action, quantum meruit and cumulative impact claims are important legal remedies that can provide substantial relief to contractors in Alaska experiencing severely disrupted projects.
Jedidiah K. Blake II and Sydney M. Sullivan are attorneys at Oles Morrison Rinker & Baker, LLP. Blake’s focus is on government contracts and construction litigation. Sullivan works with clients that span across the firm’s construction, commercial litigation, business and real estate, and government contracts groups.