Sturgeon Electric replaces the Eklutna Water Treatment Facility’s aging electrical infrastructure, including seven multi-section motor control centers, the main electrical switchgear, and other supporting electrical improvements throughout the plant. The Chugiak facility treats water from Eklutna Lake and supplies most of Anchorage’s drinking water, making it one of the municipality’s most critical pieces of public infrastructure.

Photo provided by Sturgeon Electric

Basic Needs
Strengthening Alaska’s utility infrastructure for resiliency
By Rachael Kvapil
Sturgeon Electric replaces the Eklutna Water Treatment Facility’s aging electrical infrastructure, including seven multi-section motor control centers, the main electrical switchgear, and other supporting electrical improvements throughout the plant. The Chugiak facility treats water from Eklutna Lake and supplies most of Anchorage’s drinking water, making it one of the municipality’s most critical pieces of public infrastructure.

Photo provided by Sturgeon Electric

Basic Needs
Strengthening Alaska’s utility infrastructure for resiliency
By Rachael Kvapil
U

tility costs are at the forefront of many discussions in Alaska; the state is attempting to increase efficiencies in the face of rising costs and dwindling natural gas supplies in Cook Inlet, which most Railbelt power producers rely on for electricity.

Utility projects aren’t just power lines and electrical systems. They also include building or repairing water supply mains, sanitary sewers, and stormwater management systems—essential projects that contribute to residents’ health and safety. Several such projects are currently underway across Alaska and will have a positive impact on communities big and small.

Power to the People
Sturgeon Electric is currently working on a range of projects that increase utility reliability across the state. On the top of the list is the Quartz Creek Transmission Line project, which extends from Anchorage through Indian, Girdwood, and Portage before continuing across the Kenai Peninsula to the Sterling and Quartz Creek substations. It is one of the primary high-voltage transmission lines supplying power between the Kenai Peninsula and the Anchorage Bowl.

The Quartz Creek transmission line has been modernized through a series of individual construction contracts awarded over more than a decade. Each completed segment improves system reliability, while the full benefits of the projects will be realized as the remaining sections are completed. This project is part of Chugach Electric Association’s long-term investment in replacing aging transmission infrastructure and strengthening the reliability and resiliency of Southcentral Alaska’s electrical grid. While individual contract values vary, T-line construction in Alaska typically costs between $1.25 million and $1.5 million per mile, including engineering, materials, and construction.

“Most people never think about the transmission system until the lights go out,” says Sturgeon Electric Line General Foreman Josh Henrick. “Collectively, these transmission improvements represent one of the most significant long-term investments in Southcentral Alaska’s electrical infrastructure.”

The transmission line corridor crosses avalanche terrain, wetlands, anadromous fish streams, major transportation corridors, and lands managed by multiple federal, state, and local agencies. Within this single project, crews work adjacent to the Seward Highway and Alaska Railroad, access remote mountain slopes by helicopter, and build through environmentally sensitive habitats. Henrick says the project demonstrates that reliable infrastructure and environmental stewardship are not competing objectives. Through thoughtful planning and collaboration, critical utility improvements can be delivered while protecting Alaska’s natural resources for future generations.

Sturgeon Electric crews are also installing two miles of new highway lighting, five signalized intersections, fiber-optic interconnect systems, and two automatic traffic counter stations to support traffic monitoring for future transportation planning as part of Phase II of the Seward Meridian Parkway Road Improvements. The electrical improvements are part of a larger roadway extension designed to improve traffic flow, increase safety, and accommodate continued growth in the Matanuska-Susitna Borough.

Seward Meridian Parkway is a primary north-south connector near Wasilla and serves thousands of motorists every day, including families traveling to and from four schools along its eventual length.
“Transportation infrastructure affects many Alaskans every day, whether they’re commuting to work, taking children to school, or traveling between communities,” says Sturgeon Electric Superintendent Jeremy Lutz.

The $43.5 million project is federally funded through transportation improvement programs administered by the Alaska Department of Transportation and Public Facilities. As of publication, construction is currently underway and scheduled for completion by August 31, 2026.

“Most people never think about the transmission system until the lights go out. Collectively, these transmission improvements represent one of the most significant long-term investments in Southcentral Alaska’s electrical infrastructure.”
– Josh Henrick, General Foreman, Sturgeon Electric
A Steady Stream
Among the other current Sturgeon Electric projects is the replacement of the Eklutna Water Treatment Facility’s aging electrical infrastructure, including seven multi-section motor control centers, the facility’s main electrical switchgear, and other supporting electrical improvements throughout the plant.

The Chugiak facility treats water from Eklutna Lake and sends it via pipeline to Anchorage, supplying most of the city’s drinking water. It’s one of the municipality’s most critical pieces of public infrastructure. Modernizing its electrical infrastructure helps ensure the continued reliability of the systems that treat and deliver safe drinking water to homes, businesses, schools, hospitals, and public facilities throughout the municipality.

While the project appears simple on paper, Sturgeon Electric Project Manager Chris Stafford says these systems serve as the electrical backbone of Anchorage’s primary water treatment facility. Each phase of construction must be carefully sequenced to replace critical equipment while maintaining continuous operation of the treatment process. Electrical systems are isolated, replaced, tested, and commissioned individually before the next phase begins, ensuring uninterrupted treatment operations throughout the project.

“Many infrastructure projects are highly visible,” says Stafford. “This one is different. Success is measured by what doesn’t happen: no interruption to water service, no disruption to treatment operations, and no impact to the community while critical infrastructure is upgraded behind the scenes.”

The $5 million project is funded by the Municipality of Anchorage through Anchorage Water and Wastewater Utility’s ongoing capital improvement program to modernize and maintain critical public infrastructure.

Two construction workers in high-visibility jackets and hard hats install metal pilings into muddy ground using heavy machinery, with wind turbines visible in the distance.
In Kongiganak, Kipnuk, and Kwigillingok crews continue to reconstruct boardwalks and critical infrastructure. STG started reconstruction during the first wave of recovery efforts and plans to complete the project by July of this year.

Photo provided by STG, Inc.

Two technicians in safety harnesses work high on a communications tower near large drum antennas, with one worker giving a thumbs-up against a blue sky.
STG, Inc. is managing upgrades of the Deltanet Phase 3 Upgrades that will affect several villages in the Yukon Region. This project serves as a precursor to a later project to upgrade cell service to higher bandwidth, which is required to improve service.

Photo provided by STG, Inc.

A large yellow crawler crane lifting a large cylindrical storage tank at an industrial site while a worker in high-visibility gear guides it with a tag line.
Out in Kivalina, STG, Inc. replaces aging bulk fuel and distribution infrastructure at two sites. The project includes the demolition of old bulk fuel tanks, the installation of new bulk fuel storage tanks in the raised containments, and the connection of the new systems to the existing infrastructure.

Photo provided by STG, Inc.

Connecting to Remote Communities
Several of STG, Inc.’s current utility projects are in remote and logistically challenging communities. In Kivalina, STG is replacing aging bulk fuel and distribution infrastructure at two sites. The project includes demolition of old bulk fuel tanks, containment, and systems at the power plant and community fuel storage facilities; setting up temporary systems to keep the power plant and community serviced; driving piling at both locations; installing structural steel and raised steel containments on the piling; installing new bulk fuel storage tanks in the raised containments; installing a 1,000-foot buried fill pipeline; installing a new dispensing tank and related systems for the community; and connecting the new systems to the existing infrastructure.

This project will provide a lasting bulk fuel system for the community’s only power plant. It will also provide diesel and heating oil for community residents to heat their homes and run the equipment that keeps the roads and airport operational, as well as gasoline to power the boats, ATVs, snowmachines, and other equipment that allow residents to subsist and transport themselves. The new infrastructure will also be a significant environmental protection upgrade from the current, aged-out system.

STG Program Manager Collin Pennington says constant interaction with community members is critical to minimizing day-to-day disruption to residents during such a project. STG hired community members to help keep residents informed about the work they’re doing, as well as with construction.

“STG is also working closely with the group from the other [water and wastewater upgrade] project to share both resources and the limited space within the community,” says Pennington. “We have organized joint site visits, shared lay-down space, shared equipment, and continued to coordinate schedules and give project updates. Both projects are important to the village, so ensuring their success is the goal above all else.”

This $15 million project is funded by the Denali Commission. Design began in February 2026. Construction began in early June 2026 and is anticipated to be completed in July 2027.

The Deltanet Phase 3 Upgrades managed by STG crews affect several villages in the Yukon Region. The removal and replacement of radios and antennas to increase bandwidth will ultimately bring higher-speed data to Tununak, Mekoryuk, Toksook Bay, Marshall, Pilot Station, Nunam Iqua, Chevak, Hooper Bay, Nightmute, Akiak, Akiachak, Scammon Bay, St. Mary’s, Mountain Village, Twin Hills, Togiak, Bethel, Kwethluk, Napaskiak, Napakiak, Platinum, and Goodnews Bay.

“This benefits the local population with better internet speeds,” explains STG Program Manager Jay Ubben. “It also gives the clinics and schools more capability for higher-speed virtual calls, allowing for better education and better healthcare for residents.”

Working in multiple locations requires a different approach to logistics. Ubben says STG has been working in these locations for more than thirty years and knows roughly when an area is likely to see better weather. They created camps at a couple of sites to prevent delays and also planned at least a week in advance to ensure resources were available. This allowed them to pivot between sites rather than stop and delay the whole project. STG partnered with helicopter companies to receive priority scheduling.

This project is privately funded and serves as a precursor to another project to upgrade cell service to higher bandwidth, which is required to improve service.

Other STG projects are focused on helping Western Alaska communities recover from the disastrous effects of Typhoon Halong in October 2025. In Kongiganak, Kipnuk, and Kwigillingok, crews continue to rebuild boardwalks and critical infrastructure. STG started reconstruction during the first wave of recovery efforts and wrapped up in July.

STG Program Manager Alex Lutton says boardwalks are the only means of transportation within the communities in spring and summer. In Kongiganak, STG was also tasked with building a boardwalk and path to the village’s raw water location. The community had been relying on shipped water, so establishing a path to locally available water was a priority. Crews worked seven days a week, twelve hours a day or more, living in locations without running water until the paths were built.

“Logistics teams in Bethel worked around the clock to load and coordinate charter flights to move people and supplies in and out of villages,” says Lutton.

“By connecting water and sewer to these homes [in rural Alaska], they can have water at home with a turn of a valve. It seems very simple when you live on the highway system. But when you’re somewhere where nobody has that ability, it’s new for remote residents.”
– Derrick Branson, Owner, Frostline Drilling and Construction, LLC
Enhancing Alaskans’ Lives
In July, Frostline Drilling and Construction, LLC was finalizing logistics on a raw-water intake and residential water and sewer service improvement project in Selawik. The project modernizes the rural water delivery systems, addressing shifting permafrost and seasonal freezing risks experienced in the area. It includes installing and upgrading the raw water intake system to draw a consistent supply of drinking water from the Selawik River, improving residential water and sewer utility lines to withstand the Arctic freeze-thaw cycle, and minimizing line breaks. Frostline owner Derrick Branson says the projects give residents access to resources they may not have had before.

“Some of these homes have five children and two generations of parents, and they don’t have running water or sewer,” says Branson. “By connecting water and sewer to these homes, they can have water at home with a turn of a valve. It seems very simple when you live on the highway system. But when you’re somewhere where nobody has that ability, it’s new for remote residents.”

The $1.5 million project is managed by the Alaska Native Trial Health Consortium and is expected to be completed by September.

Branson says Frostline Drilling and Construction has several other utility projects currently in the works, including a $196,660 residential water service line and sewage holding tank installation project in Galena; a $183,390 residential well and septic system installation in Glenallen; and a $431,400 residential water and sewer service line installation project in Kotzebue.

Rachael Kvapil is a freelance writer who lives in Fairbanks.